Project # 249000 Project: Sewer Line Installation Location: Jefferson Township Owner: Jefferson
Township Start: November, 2002 Completion: July, 2004 Cost: 6,687,300.26 Design: Acker Associates |
|
|
Jefferson Township Municipal Authority put six sewer bids out, Leeward Construction was awarded four of the bids totaling over six million dollars. The projects encompassed miles of sewer line (gravity and force main), stream and road crossings, service connections, grinder pump hook ups, Penn DOT pavement restoration and lawn restoration. |
|